Detroit, MI

Marathon Administration Building

Angelo Iafrate Construction Company has completed numerous projects at The Marathon complex over the years. Even though the Administration Building is being constructed away from the Refinery, the stringent background checks, drug testing and safety requirements were still enforced. Because of our History working there we had no issues.

This projected consisted of three independent parking lots North, East, West and concrete paving. Additionally, the project was supposed to begin late summer but due to schedule issues was pushed to late fall which meant cold weather concrete had to be implemented.

Fast Facts

Project Name: Marathon Administration Building
Location: Detroit, MI
Owner/Client: Marathon/Walbridge
Engineer: Manick Smith

  • 6,500 lf of Curb and Gutter
  • 61,000 sft of 4” Sidewalk
  • Integral Curb and Walk